| Related Topics: | ||
A complex system is under design. The reliability team wants to create an overall reliability growth plan based on the Crow Extended model. The inputs to the model are the following:
Find the following:
Based on Eqn. (8), the growth potential MTBF is:

From Eqn. (6), the growth potential failure intensity is:

The initial failure intensity is given by Eqn. (7):

From Eqn. (4), the Type A failure mode intensity, λA, is:

From Eqn. (5), the Type B failure mode intensity, λB, is:
(24)
Using the inputs of λB and β in Eqn. (18) we have:

or:
![]()
or:

The Type B failure mode discovery function is:
![]()
Since we know the λ and β parameters, we have:

Based on Eqn. (13), the initialization time, t0, is:

or:
![]()
Based on Eqns. (10) and (11), the nominal idealized growth curve is given by the following equation:

or:

Based on Eqn. (14), the nominal time to reach the MTBF goal is:

For the goal failure intensity we have:

So the nominal time to reach the MTBF goal is:

Using Eqn. (10) we find the failure intensity that can be reached at the end of the last test phase based on the nominal idealized growth curve, rNI,final. The total (cumulative) test time is T = 4500 hours. Therefore we have:

So the nominal final MTBF that can be reached at 4500 hours of test time is:

We can find the actual initialization time by using Eqn. (20):

For question 6, we had found that t0 = 14.07. So we have:

The failure intensity that can be reached at the end of the last test phase based on the actual idealized growth curve is given by Eqn. (21) for T = 4500 hours:

Therefore:

Therefore:
![]()
So the actual final MTBF that can be reached at 4500 hours of test time is:

From question 11, it is shown that the actual final MTBF that can be reached at 4500 hours of test time is less than the MTBF goal for the program. So, in accordance with the third case that is described in the Crow Extended Model - Reliability Growth Planning section of this on-line reference, this is the scenario where the actual time to meet the MTBF goal will not be calculated since the reliability growth program needs to be redesigned.
The failure intensity that can be reached at the end of the last test phase based on the actual idealized growth curve is given by Eqn. (21) for T = T3 = 6000 hours:

Therefore:

Therefore:
![]()
So, the actual final MTBF that can be reached at 6000 hours of test time is:

In this case, the actual MTBF goal becomes higher than the target MTBF sometime during the last phase. Using Eqn. (23), we can determine the actual time to reach the MTBF goal:

Therefore:

Then:
![]()
In the RGA 7 Project Explorer we right-click Growth Planning and select Add Growth Planning. We then specify the number of phases, and the cumulative phase time and average fix delays for each of the three phases, as shown in Figure 11.1.

Figure 11.1: Specifying number of phases, phase time and average fix delay |
When we click the Calculate icon, the input window for the Crow Extended model parameters appears, as shown in Figure 11.2. The input provided is the required MTBF goal of 56, the growth potential design margin of 1.35, the management strategy of 0.95 and the discovery beta of 0.7. The results show the initialization time, t0, the initial MTBF, the final actual MTBF that can be reached for this growth program and the actual time when the MTBF goal is met. Note that in this case we provided the goal MTBF and solved for the initial MTBF.

Figure 11.2: Inputs for the Crow Extended model, when calculating the initial MTBF |
Different calculation options are available depending on the desired input and output. For example we could provide the initial and goal MTBF and solve for the growth potential design margin, as shown in Figure 11.3.

Figure 11.3: Inputs for the Crow Extended model when calculating the Growth Potential Design Margin |
By clicking the Calculate icon in the Planning Calculations window, we can then return to the main growth planning window where the planning information and results are presented, as shown in Figure 11.4.

Figure 11.4: Growth Planning window showing phase information, model inputs and results |
By clicking the Plot icon, we can then generate a plot that shows the nominal and actual idealized growth curve, the test termination time, the MTBF goal and the planned growth for each phase, as shown in Figure 11.5.

Figure 11.5: Growth planning plot |
The reliability team of a product manufacturer is putting together a reliability growth plan for one of the new products under design. The reliability team wants to create an overall reliability growth plan based on the Crow Extended model. The inputs to the model are the following:
Construct a reliability growth plan with RGA 7 and make sure that the goal MTBF can be met within the total test hours allocated for growth testing. If not, make necessary changes in the phase durations in order to meet the goal.
Figure 11.6 shows the planning input in RGA 7, in terms of test phases and average fix delays.

Figure 11.6: Growth planning in seven phases |
Figure 11.7 shows the planning calculations based on the goal MTBF of 100 hours and the rest of the known inputs into the model. As seen by the planning calculation results, the final actual MTBF at the end of the seventh phase is 98.66 hours, which is less than the MTBF goal of 100 hours. Also, in Figure 11.8, it is shown that the nominal time to meet the MTBF goal is 48420 hours, which is higher than the total test time that is currently planned to be allocated for reliability growth.

Figure 11.7: Planning model inputs and results for the initial plan |

Figure 11.8: Planning model with results for the initial plan |
A new plan needs to be considered. The reliability team decides to increase the test time for Phases 5 and 6 to be 10000 hours each, instead of the 5000 hours that were considered in the initial plan. Also, the team decides to increase the duration of the seventh phase to 15000 hours. Since this is going to be achieved by testing for more calendar time in Phases 5, 6 and 7, the average fix delay during those phases is the same as the one in the initial plan. The test time per week is not going to be affected, only more weeks will be added to the schedule. Figure 11.9 shows the revised plan, together with the calculated results. The actual time to meet the MTBF goal is now 54331 hours. The final MTBF that can be achieved at the end of the 55000 hours of growth testing is 100.04, which is slightly higher than the goal MTBF of 100 hours. The reliability team considers this plan as acceptable, since the MTBF goal will be met. Figure 11.10 shows the overall reliability growth plan, with the nominal and actual growth curves, the MTBF goal line and the planned MTBF for each of the seven phases.

Figure 11.9: Reliability growth plan with revised phase durations |

Figure 11.10 Growth planning plot for the seven phases with the revised plan |
The reliability team of a product manufacturer has put together a reliability growth plan, based on the Crow Extended model, for one of their new products. The reliability growth model was constructed with the following inputs:

Figure 11.11: Phase 1 data, analyzed with the Crow Extended - Continuous Evaluation model |

Figure 11.12: Fixed effectiveness factor and phase of implementation for unfixed BD modes in Phase 1 |
Construct a multi-phase graph that shows the analysis points for the test data in Phase 1, as compared to the nominal and actual idealized growth curves for this reliability growth plan. Is the program on track, so far, as compared to the plan?

Figure 11.13: Inputs in reliability growth planning model |

Figure 11.14: Reliability growth planning information and results |

Figure 11.15: Nominal and actual idealized growth curves with planned growth in four phases |
The Multiple Phase Plot can be continuously updated as the growth program progresses and more test data becomes available. In that manner, the reliability team can assess actual reliability performance against the established goals.

Figure 11.16: Multi-Phase plot containing the overall growth plan and the actual test results for Phase 1 |