General Examples Using the Crow Extended Model

Crow Extended Example 5

Three systems were subjected to a reliability growth test to test the prototype of a new product. Once the test was completed a failure analysis was done and based on this a management strategy was able to be defined. It was determined that all corrective actions will be delayed until after the test. The collected data is shown in Table 9.4 and the associated effectiveness factors for each unique BD mode are presented in Table 9.5. The prototype is required to meet a projected MTBF goal of 55 hours. Do the following:

  1. Estimate the parameters of the Crow Extended model.

  2. Based on the current management strategy what is the projected MTBF?

  3. If the projected MTBF goal is not met, alter the current management strategy to meet this requirement with as little adjustment as possible without changing the EF of the existing BD modes. Assume an EF = 0.7 for any newly assigned BD modes.

Table 9.4 - Multiple Systems (Unknown Equivalent Times) data for Crow Extended Example 5

 

System 1

System 2

System 3

Start Time

0

0

0

End Time

541

454

436

Times-to-Failure

83 BD37

26 BD25

23 BD30

 

83 BD43

26 BD43

46 BD49

 

83 BD46

57 BD37

127 BD47

 

169 A45

64 BD19

166 A2

 

213 A18

169 A45

169 BD23

 

299 A42

213 A32

213 BD7

 

375 A1

231 BD8

213 BD29

 

431 BD16

231 BD25

255 BD26

 

 

231 BD27

369 A33

 

 

231 A28

374 BD29

 

 

304 BD24

380 BD22

 

 

383 BD40

415 BD7

Table 9.5 - Effectiveness factors for Crow Extended Example 5

BD Mode

Effectiveness Factor

30

0.75

43

0.5

25

0.5

49

0.75

37

0.9

19

0.75

46

0.75

47

0.25

23

0.5

7

0.25

29

0.25

8

0.5

27

0.5

26

0.75

24

0.5

22

0.5

40

0.75

16

0.75

Solution to Crow Extended Example 5

  1. The estimated Crow Extended parameters are shown in Figure 9.12.

  2. There are a couple of ways to calculate the projected MTBF, but the easiest is via the Quick Calculation Pad (QCP), as shown in Figure 9.13.

  3. From the previous question, the projected MTBF is estimated to be 53.9390 hours which is below the goal of 55 hours. To reach our goal, or to see if we can even get there, the management strategy must be changed. The effectiveness factors for the existing BD modes cannot be changed, however it is possible to change an A mode to a BD mode. But which A mode(s) should be changed? To answer this question, you can view the Individual Mode Failure Intensity plot while just displaying the A modes as shown in Figure 9.14. As you can see from the plot, failure mode A45 has the highest failure intensity. Therefore, among the A modes this particular failure mode is having the greatest negative effect in regards to the system MTBF. So change A45 to BD45. Be sure to change all instances of A45 to a BD mode. Enter an effectiveness factor for BD45 equal to 0.7 and recalculate the parameters of the Crow Extended model. Now go back to the QCP to calculate the projected MTBF as shown in Figure 9.15. The projected MTBF is now estimated to be 55.5903 hours. Based on the change in the management strategy, the projected MTBF goal is now expected to be met.

Figure 9.12: Entered data and the estimated Crow Extended parameters

Figure 9.13: Calculate the projected MTBF

Figure 9.14: Individual Mode Failure Intensity plot

Figure 9.15: Calculate the projected MTBF based on the change to the management strategy.

Crow Extended Example 6

A reliability growth test was conducted for 200 hours. Some of the corrective actions were applied during the test while others were delayed until after the test was completed. The data is given in Table 9.6. The effectiveness factors for the BD modes are given in Table 9.7. Do the following:

  1. Estimate the parameters of the Crow Extended model.

  2. Determine the average effectiveness factor of the BC modes using the Function Wizard.

  3. What percent of the failure intensity will be left in the system due to the BD modes after implementing the delayed fixes?

Table 9.6 - Grouped Failure Times data for Crow Extended Example 6

Number at Event

Time to Event

Classification

Mode

3

25

BC

1

1

25

BD

1

1

25

BC

2

1

50

BD

2

1

50

BD

3

1

75

BD

4

1

75

BC

3

2

75

BD

5

1

75

A

 

1

100

BC

4

1

100

BD

6

1

125

BD

7

1

125

A

 

1

125

A

 

1

125

BC

5

1

125

BD

2

1

125

BC

6

1

150

A

 

1

150

BD

8

1

175

BC

4

1

175

BC

8

1

175

A

 

1

175

BC

9

1

200

BD

8

1

200

BC

3

1

200

BD

9

Table 9.7 - Effectiveness factors for Example 6

BD Mode

Effectiveness Factor

1

0.75

2

0.5

3

0.9

4

0.6

5

0.8

6

0.8

7

0.25

8

0.75

9

0.8

Solution to Crow Extended Example 6

  1. The estimated parameters of the Crow Extended model are shown in Figure 9.16.

  2. After inserting a General Spreadsheet into the Folio, the Function Wizard can be accessed via the Tools menu. Once the Function Wizard is loaded select Average Effectiveness Factor from the list of available functions and under Avg. Eff. Factor select BC modes as shown in Figure 9.17. Click OK and the result will be placed into the General Spreadsheet. The average effectiveness factor for the BC modes is 0.6983.

  3. The percent of the failure intensity left in the system due to the BD modes can be determined using the Failure Mode Strategy plot as shown in Figure 9.18. Therefore, the percent of the failure intensity left in the system due to the BD modes is 1.79%.

Figure 9.16: Entered data and the estimated Crow Extended parameters

Figure 9.17: Calculate the average effectiveness factor for the BC modes using the Function Wizard

Figure 9.18: Failure Mode Strategy plot

Crow Extended Example 7

Two prototypes of a new design are tested simultaneously. The test was terminated after 300 hours. All of the design changes for the prototypes were delayed until after completing the test and the data is given in Table 9.8. Assume a fixed effectiveness factor equal to 0.7. The MTBF goal for the new design is 30 hours. Do the following:

  1. Estimate the parameters of the Crow Extended model.

  2. What is the projected MTBF and growth potential?

  3. Under the current management strategy is it even possible to reach the MTBF goal of 30 hours?

Table 9.8 - Multiple Systems (Known Equivalent Times) data for Example 7

Failed Unit ID

Time Unit 1

Time Unit 2

Classification

Mode

1

16.5

0

BD

seal leak

1

16.5

0

BD

valve

1

17

0

A

 

2

20.5

0.9

A

 

2

25.3

3.8

BD

hose

2

28.7

4.6

BD

operator error

1

41.8

14.7

BD

bearing

1

45.5

17.6

A

 

2

48.6

22

A

 

2

49.6

23.4

BD

seal leak

1

51.4

26.3

A

 

1

58.2

35.7

BD

seal leak

2

59

36.5

A

 

2

60.6

37.6

BD

hose

1

61.9

39.1

BD

seal leak

1

76.6

55.4

BD

bearing

2

81.1

61.1

A

 

1

84.1

63.6

A

 

1

84.7

64.3

A

 

1

94.6

72.6

A

 

2

100

78.1

BD

valve

1

104

81.4

BD

bearing

2

104.8

85.9

BD

spring

2

105.9

87.1

BD

operator error

1

108.8

89.9

BD

hose

2

132.4

119.5

BD

spring

2

132.4

150.1

BD

operator error

2

132.4

153.7

A

 

Solution to Crow Extended Example 7

  1. The estimated Crow Extended parameters are shown in Figure 9.19.

  2. One possible method to calculate the projected MTBF and growth potential is to use the Quick Calculation pad, but you can also view these two values at the same time by viewing the Growth Potential MTBF plot which is displayed in Figure 9.20. From the plot, the projected MTBF is equal to 16.87 hours and the growth potential is equal to 18.63.

  3. The current projected MTBF and growth potential are both well below the required goal of 30 hours. To check if this goal can even be reached, you can set the effectiveness factor equal to one. In other words, if all of the corrective actions were to remove the failure modes completely then what would be the projected and growth potential MTBF? After changing the fixed effectiveness factor to one, the parameters are recalculated and the Growth Potential plot is refreshed. The refreshed plot is shown in Figure 9.21. Even if you assume an effectiveness factor equal to one, the growth potential is still only 27.27 hours. Based on the current design process it will not be possible to reach the MTBF goal of 30 hours. Therefore, there are basically two options: start a new design stage or quite possibly reduce the required goal.

Figure 9.19: Entered data and the estimated Crow Extended parameters

Figure 9.20: Growth Potential MTBF plot (EF = 0.7)

Figure 9.21: Growth Potential MTBF plot (EF = 1)

 

See Also:
Crow Extended


 Go to weibull.com
Go to ReliaSoft.com

©1992-2005. ReliaSoft Corporation. ALL RIGHTS RESERVED.