| Related Topics: | ||
Three systems were subjected to a reliability growth test to evaluate the prototype of a new product. Once the test was completed a failure analysis was done and, based on this, a management strategy was able to be defined. It was determined that all corrective actions will be delayed until after the test. The collected data set is shown in Table 9.6 and the associated effectiveness factors for each unique BD mode are presented in Table 9.6. The prototype is required to meet a projected MTBF goal of 55 hours. Do the following:
Table 9.6 - Multiple Systems (Concurrent Operating Times) data for Example 8
|
System 1 |
System 2 |
System 3 |
Start Time |
0 |
0 |
0 |
End Time |
541 |
454 |
436 |
Times-to-Failure |
83 BD37 |
26 BD25 |
23 BD30 |
|
83 BD43 |
26 BD43 |
46 BD49 |
83 BD46 |
57 BD37 |
127 BD47 |
|
169 A45 |
64 BD19 |
166 A2 |
|
213 A18 |
169 A45 |
169 BD23 |
|
299 A42 |
213 A32 |
213 BD7 |
|
375 A1 |
231 BD8 |
213 BD29 |
|
431 BD16 |
231 BD25 |
255 BD26 |
|
|
231 BD27 |
369 A33 |
|
|
231 A28 |
374 BD29 |
|
|
304 BD24 |
380 BD22 |
|
|
383 BD40 |
415 BD7 |
Table 9.7 - Effectiveness factors for Example 8
BD |
Effectiveness |
30 |
0.75 |
43 |
0.5 |
25 |
0.5 |
49 |
0.75 |
37 |
0.9 |
19 |
0.75 |
46 |
0.75 |
47 |
0.25 |
23 |
0.5 |
7 |
0.25 |
29 |
0.25 |
8 |
0.5 |
27 |
0.5 |
26 |
0.75 |
24 |
0.5 |
22 |
0.5 |
40 |
0.75 |
16 |
0.75 |

Figure 9.29: Entered data and the estimated Crow Extended parameters |

Figure 9.30: Calculate the projected MTBF |

Figure 9.31: Individual Mode Failure Intensity chart |

Figure 9.32: Calculate the projected MTBF based on the change to the management strategy |
A reliability growth test was conducted for 200 hours. Some of the corrective actions were applied during the test while others were delayed until after the test was completed. The data set is given in Table 9.8. The effectiveness factors for the BD modes are given in Table 9.9. Do the following:
Table 9.8 - Grouped Failure Times data for Example 9
Number |
Time |
Classification |
Mode |
3 |
25 |
BC |
1 |
1 |
25 |
BD |
9 |
1 |
25 |
BC |
2 |
1 |
50 |
BD |
10 |
1 |
50 |
BD |
11 |
1 |
75 |
BD |
12 |
1 |
75 |
BC |
3 |
2 |
75 |
BD |
13 |
1 |
75 |
A |
|
1 |
100 |
BC |
4 |
1 |
100 |
BD |
14 |
1 |
125 |
BD |
15 |
1 |
125 |
A |
|
1 |
125 |
A |
|
1 |
125 |
BC |
5 |
1 |
125 |
BD |
10 |
1 |
125 |
BC |
6 |
1 |
150 |
A |
|
1 |
150 |
BD |
16 |
1 |
175 |
BC |
4 |
1 |
175 |
BC |
8 |
1 |
175 |
A |
|
1 |
175 |
BC |
7 |
1 |
200 |
BD |
16 |
1 |
200 |
BC |
3 |
1 |
200 |
BD |
17 |
Table 9.9 - Effectiveness factors for Example 9
BD |
Effectiveness |
9 |
0.75 |
10 |
0.5 |
11 |
0.9 |
12 |
0.6 |
13 |
0.8 |
14 |
0.8 |
15 |
0.25 |
16 |
0.75 |
17 |
0.8 |

Figure 9.33: Entered data and the estimated Crow Extended parameters |

Figure 9.34: Calculate the average effectiveness factor for the BC modes using the Function Wizard |

Figure 9.35: Failure Mode Strategy plot |
Two prototypes of a new design are tested simultaneously. Whenever a failure was observed for one unit, the current operating time of the other unit was also recorded. The test was terminated after 300 hours. All of the design changes for the prototypes were delayed until after completing the test and the data set is given in Table 9.10. Assume a fixed effectiveness factor equal to 0.7. The MTBF goal for the new design is 30 hours. Do the following:
Table 9.10 - Multiple Systems (Known Operating Times) data for Example 10
Failed |
Time |
Time |
Classification |
Mode |
1 |
16.5 |
0 |
BD |
seal leak |
1 |
16.5 |
0 |
BD |
valve |
1 |
17 |
0 |
A |
|
2 |
20.5 |
0.9 |
A |
|
2 |
25.3 |
3.8 |
BD |
hose |
2 |
28.7 |
4.6 |
BD |
operator error |
1 |
41.8 |
14.7 |
BD |
bearing |
1 |
45.5 |
17.6 |
A |
|
2 |
48.6 |
22 |
A |
|
2 |
49.6 |
23.4 |
BD |
seal leak |
1 |
51.4 |
26.3 |
A |
|
1 |
58.2 |
35.7 |
BD |
seal leak |
2 |
59 |
36.5 |
A |
|
2 |
60.6 |
37.6 |
BD |
hose |
1 |
61.9 |
39.1 |
BD |
seal leak |
1 |
76.6 |
55.4 |
BD |
bearing |
2 |
81.1 |
61.1 |
A |
|
1 |
84.1 |
63.6 |
A |
|
1 |
84.7 |
64.3 |
A |
|
1 |
94.6 |
72.6 |
A |
|
2 |
100 |
78.1 |
BD |
valve |
1 |
104 |
81.4 |
BD |
bearing |
2 |
104.8 |
85.9 |
BD |
spring |
2 |
105.9 |
87.1 |
BD |
operator error |
1 |
108.8 |
89.9 |
BD |
hose |
2 |
132.4 |
119.5 |
BD |
spring |
2 |
132.4 |
150.1 |
BD |
operator error |
2 |
132.4 |
153.7 |
A |
|

Figure 9.36: Entered data and the estimated Crow Extended parameters |

Figure 9.37: Growth Potential MTBF plot (EF = 0.7) |

Figure 9.38: Growth Potential MTBF plot (EF = 1) |