Related Topics: toprightheader.gif

Crow-AMSAA (NHPP) Model

Time-to-Failure Data

Discrete (Success/Failure) Data

Fielded Systems Data

General Examples Using the Crow-AMSAA Model

Crow-AMSAA Example 11

Six systems were subjected to a reliability growth test and a total of 81 failures were observed. Table 5.9 presents the start and end times, along with the times-to-failure for each system. Do the following:

  1. Estimate the parameters of the Crow-AMSAA model using maximum likelihood estimation.
  2. How many additional failures would be generated if testing continues until 3000 hours?

Table 5.9 - Multiple systems (concurrent operating times) data for Example 11

System #

1

2

3

4

5

6

Start Time

0

0

0

0

0

0

End Time

504

541

454

474

436

500

Times-to-Failure

21

83

26

36

23

7

 

29

83

26

306

46

13

 

43

83

57

306

127

13

 

43

169

64

334

166

31

 

43

213

169

354

169

31

 

66

299

213

395

213

82

 

115

375

231

403

213

109

 

159

431

231

448

255

137

 

199

 

231

456

369

166

 

202

 

231

461

374

200

 

222

 

304

 

380

210

 

248

 

383

 

415

220

 

248

 

 

 

 

422

 

255

 

 

 

 

437

 

286

 

 

 

 

469

 

286

 

 

 

 

469

 

304

 

 

 

 

 

 

320

 

 

 

 

 

 

348

 

 

 

 

 

 

364

 

 

 

 

 

 

404

 

 

 

 

 

 

410

 

 

 

 

 

 

429

 

 

 

 

 

Solution to Crow-AMSAA Example 11
  1. Figure 5.28 shows the parameters estimated using RGA.
  2. The number of failures can be estimated using the Quick Calculation Pad as shown in Figure 5.29. The estimated number of failures at 3000 hours is equal to 83.2451 and 81 failures were observed during testing. Therefore, the number of additional failures generated if testing continues until 3000 hours is equal to 83.2451 - 81 = 2.2451 ≈ 3.

Figure

Figure 5.28: Estimated parameters of the Crow-AMSAA model

Figure

Figure 5.29: Expected number of failures at 3000 hours

Crow-AMSAA Example 12

A prototype of a system was tested at the end of one of its design stages. The test was run for a total of 300 hours and 27 failures were observed. Table 5.10 shows the collected data set. The prototype has a design specification of an MTBF equal to 10 hours with a 90% confidence level at 300 hours. Do the following:

  1. Estimate the parameters of the Crow-AMSAA model using maximum likelihood estimation.
  2. Does the prototype meet the specified goal?

Table 5.10 - Failure times data for Example 12

2.6

56.5

98.1

190.7

16.5

63.1

101.1

193

16.5

70.6

132

198.7

17

73

142.2

251.9

21.4

77.7

147.7

282.5

29.1

93.9

149

286.1

33.3

95.5

167.2

 

Solution to Crow-AMSAA Example 12
  1. Figure 5.30 shows the parameters estimated using RGA.
  2. The instantaneous MTBF with one-sided 90% confidence bounds can be calculated using the Quick Calculation Pad (QCP) as shown in Figure 5.31. From the QCP, it is estimated that the lower limit on the MTBF at 300 hours with a 90% confidence level is equal to 10.8170 hours. Therefore, the prototype has met the specified goal.

Figure

Figure 5.30: Estimated parameters of the Crow-AMSAA model

Figure

Figure 5.31: Instantaneous MTBF with one-sided 90% confidence bounds

Crow-AMSAA Example 13

A one-shot system underwent reliability growth development for a total of 50 trials. The test was performed as a combination of configuration in groups and individual trial by trial. Table 5.11 shows the obtained test data set. The first column specifies the number of failures that occurred in each interval and the second column the cumulative number of trials in that interval. Do the following:

  1. Estimate the parameters of the Crow-AMSAA model using maximum likelihood estimators.
  2. What are the instantaneous reliability and the 2-sided 90% confidence bounds at the end of the test?
  3. Plot the cumulative reliability with 2-sided 90% confidence bounds.
  4. If the test was continued for another 25 trials what would the expected number of additional failures be?

Table 5.10 - Mixed data for Example 13

Failures in Interval

Cumulative Trials

3

4

0

5

4

9

1

12

0

13

1

15

2

19

1

20

1

22

0

24

1

25

1

28

0

32

2

37

0

39

1

40

1

44

0

46

1

49

0

50

Solution to Crow-AMSAA Example 13
  1. Figure 5.32 shows the parameters estimated using RGA.

rga7_ch5amsaa_mixed_data.wmf

Figure 5.32: Estimated parameters of the Crow-AMSAA model

  1. Figure 5.33 shows the calculation of the instantaneous reliability with the 2-sided 90% confidence bounds. From the QCP it is estimated that the instantaneous reliability at stage 50 (or at the end of the test) is 0.7487 with an upper and lower 2-sided 90% confidence bound of 0.8424 and 0.3815 respectively.

    rga7_ch5amsaa_mixed_qcp.wmf

    Figure 5.33: Instantaneous reliability with 2-sided 90% confidence bounds

  2. Figure 5.34 shows the plot of the cumulative reliability with the 2-sided 90% confidence bounds.

    rga7_ch5amsaa_mixed_reliability_plot.wmf

    Figure 5.34: Plot of cumulative reliability with 2-sided 90% confidence bounds

  3. Figure 5.35 shows the calculation of the expected number of failures after 75 trials. From the QCP it is estimated that the cumulative number of failures after 75 trials is 26.3770 ≈ 27. Since 19 failures occurred in the first 50 trials, the estimated number of additional failures is 6.

    rga7_ch5amsaa_mixed_qcp_cumfailures.wmf

    Figure 5.35: Cumulative number of failures after 75 trials